Part of: Construction and improvement works
This major works programme concentrates on the external areas to all blocks, except Rochford and Martlesham, which are part of the pilot refurbishment project.
Works include:
This works programme is starting in October 2025. This will be a phased programme of works, which we expect to complete by August 2026.
The undercrofts at Broadwater Farm are the car park and communal spaces underneath the blocks.
These spaces are used for more than parking cars. They are also walkways and block entrance spaces for residents and visitors and need to feel safe and welcoming for everyone.
Debden will be the first to trial the improvements to the undercroft areas including:
If successful, we'll apply them across the estate. This pilot project will start in autumn 2025.
Visit the improvement programme works update page on the Broadwater Farm Engagement Hub to learn more.